Estimate as of 4 March 2024
The below chart is the estimated nuclear waste volumes by unit as part of Bruce Power’s Major Component Replacement Project, which began in Unit 6 on January 17, 2020.
To learn more, visit www.brucepower.com/life-extension-program-mcr-project.
Unit 6 Actuals | Unit 3 | Unit 4 | Unit 5 | Unit 7 | Unit 8 | |
---|---|---|---|---|---|---|
Outage Period | Q1 2020 – Q4 2023 Actuals | Q1 2023 – Q2 2026 | Q1 2025 – Q4 2027 | Q2 2026 – Q4 2029 | Q2 2028 – Q2 2031 | Q2 2030 – Q2 2033 |
Low Level Waste (LLW) | 477 m3 | 432 m3 | 432 m3 | 440 m3 | 440 m3 | 440 m3 |
Intermediate Level Waste (ILW) | 6 m3 | 14 m3 | 14 m3 | 9 m3 | 9 m3 | 9 m3 |
Reactor Components Waste (In shielded storage/disposal containers) | 382 m3 | 382 m3 | 382 m3 | 382 m3 | 382 m3 | 382 m3 |
Steam Generators (LLW) (8 per Unit; as delivered/Intact) | 330 m3 | 349 m3 | 349 m3 | 330 m3 | 330 m3 | 330 m3 |